We use first and third-party cookies and other tracking technologies partner (Microsoft Clarity, Google Analytics, and Microsoft Advertising) to better undersand how you use and interact with our website. We use this information for site optimization, fraud/security purposes, and advertising. For more information, visit the Privacy Statement. Close

 

ARTICLE SUMMARY

  • A completed configuration checklist does not prove a plant is ready to operate with MES. Go-live approval should depend on demonstrated operational readiness.
  • Eight questions help manufacturers evaluate scope, defects, users, integrations, data, support, recovery procedures, and production ownership before launch.
  • Clear go/no-go criteria turn an approaching deadline into an evidence-based decision rather than a judgment made under schedule pressure.

The software is configured, the project schedule shows a launch date, and the team is preparing to begin production with MES.

… But being finished with configuration is not the same as being ready to operate.

The decision should depend on whether people, processes, information, and support are prepared to work together.

Today we take a closer look at how manufacturers can decide whether their MES is ready for go-live and what should be resolved before they say yes.

Readiness Starts BEFORE Launch Week

What should you check before starting an MES project?

Begin with business objectives, existing processes, team responsibilities, integration needs, and the people who will use the system.

Rain Engineering’s MES Implementation Checklist carries those considerations through planning, technology setup, deployment, training, and optimization. It recommends using the checklist repeatedly, not simply completing it once.

That distinction matters at go-live. Early planning identifies what the project must accomplish. The readiness review establishes whether the agreed scope can now operate.

The following eight questions turn those planning considerations into a practical decision framework.

– Question One: Have We Agreed on What Is Going Live?

Everyone approving launch should understand which lines, products, workflows, users, and interfaces are included. They should also understand what remains outside the initial scope.

Without that agreement, people may approve different versions of “ready.” Establish one shared description of the operating scope and obtain acceptance from the affected business owners.

The approval should cover the actual production activities being introduced, not simply confirm that the configured software matches the project plan.

– Question Two: Are Critical Problems Resolved?

An issue count alone does not tell the team whether it is safe or practical to proceed. The decision needs to distinguish minor inconveniences from problems that prevent required production or quality activities.

Define launch-blocking conditions before the final meeting. Review remaining issues against those conditions, including the effectiveness of any proposed workaround.

A workaround should have an owner and an approved operating procedure. It should not depend on someone informally promising to watch the system. Record the remaining risk, the mitigation, and the person responsible for follow-up.

– Question Three: Can Users Perform Their Jobs?

Training attendance is useful evidence, but it should not be the only evidence. Ask whether operators, supervisors, quality personnel, and administrators can complete their assigned work using the access they will actually have.

Include people from every affected shift. They should understand normal tasks, exception handling, and where to get help.

Rain’s checklist includes role-based training, hands-on floor sessions, super users, and help channels. Velotic’s MES implementation guidance also emphasizes validating workflows with real operators.

– Question Four: Have the Integrations Been Verified?

A successful connection does not prove that the complete production workflow works.

Verify that required information reaches the correct destination and produces the intended result. Also establish what users should do when another system is unavailable.

For each interface included in the launch scope, test expected operating volumes and interruption scenarios. The review should establish whether the workflow works under the conditions the plant expects to encounter.

– Question Five: Do the Production Records Agree?

Before approval, establish whether the MES records reconcile with the agreed source information.

Check the relevant orders, materials, quantities, statuses, and production relationships. Investigate differences instead of accepting a report simply because it displays plausible numbers.

The owners of the information should approve the reconciliation results. Review loaded data for completeness, duplication, and accuracy, and apply comparable scrutiny to ongoing production transactions.

– Question Six: Is Support Available When Production Runs?

Support readiness means more than having a contact name.

Operators need a clear reporting route. Support personnel need access, troubleshooting information, and an escalation path. Coverage should match the launch schedule and affected shifts.

Confirm who will respond, what they can resolve, and who takes over when a problem exceeds their authority. Make sure the support team has received the knowledge needed to troubleshoot the implemented solution.

– Question Seven: Can We Recover if Launch Cannot Continue?

Before go-live, decide what would trigger a pause, rollback, or approved fallback process.

The plan should explain who makes that decision, how production continues or stops, and how records are protected. A backup is one recovery component, not a complete operating plan.

Rain Engineering’s checklist includes backups and phased deployment. Build on those points with a rehearsed cutover and recovery procedure appropriate to the plant’s processes.

– Question Eight: Who Owns the Decision and the Operation?

The implementation team can explain technical readiness. The business must accept responsibility for operating with the system.

Name the decision authority and the owners of production workflows, quality requirements, information, and support. Record unresolved conditions and who is accountable for them.

The central requirement is evidence. A launch date creates a target; it does not prove readiness. Approval should reflect demonstrated capability and explicit acceptance by the people responsible for the operation.

The Deep Dive: The Technical Readiness Review

Now that we have covered the eight questions, we will examine the technical aspects of answering them, including test evidence, defect thresholds, transaction reconciliation, cutover controls, and recovery procedures.

Define Go/No-Go Criteria Before Reviewing Results

Create a readiness record that links each approval condition to its evidence, owner, and decision status. This is the working record behind the launch meeting.

Write criteria so reviewers can determine whether they have been met. “Integrations tested” is too broad. Identify the required workflows, expected outcomes, performance requirements, and recovery behavior.

Do not impose a generic threshold simply because it sounds rigorous. The relevant acceptance limits should reflect the plant’s operating requirements and the consequences of failure.

Connect each test cycle to defined exit criteria and approval by the relevant business owner. At the cutover checkpoint, stakeholders should review the results against those criteria rather than rely on a general impression of progress.

Establish the decision rule in advance. Launch-blocking criteria should remain blocking unless the designated authority approves a documented, permissible alternative. Schedule pressure should not quietly redefine acceptance.

Tie Defect Severity to Operational Consequences

Use the defect register to show the affected workflow, severity, reproducibility, owner, and current disposition.

Classify severity by consequences, not by how difficult a fix appears. Consider whether the issue prevents required work, compromises record integrity, disrupts traceability, or undermines an applicable quality control.

A proposed workaround needs validation. Record who performs it, the access required, its operating limits, and how resulting transactions will be checked. Determine whether it remains practical across shifts and expected workload.

Retest corrected defects and the related workflows. Closing a development ticket should not automatically close the readiness condition.

For deferred issues, document business acceptance, monitoring, an accountable owner, and a resolution target. The readiness record should make clear why each remaining issue does or does not prevent launch.

Test Complete Workflows with Representative Users

User acceptance testing, or UAT, should establish that the configured system supports the work people are expected to perform.

Use representative production data and actual role permissions in an environment that reasonably approximates production. Include normal tasks and relevant exception scenarios, and obtain approval from the responsible business owners.

For MES readiness, define the applicable transaction sequence from work preparation through production recording and completion. Include the exceptions required by the operating scope, rather than testing only the simplest path.

Record expected and actual results. Separate a training gap from a configuration defect, but resolve both before approving the affected activity.

Velotic recommends piloting MES in a controlled production area and validating workflows with real operators. That reinforces the distinction between demonstrating software to users and demonstrating that users can operate it.

Verify Interfaces, Performance, and Reconciliation Together

System integration testing, or SIT, should follow a transaction across application boundaries.

Verify identifiers, field mapping, units, timestamps, statuses, and destination records. Include the relevant ERP, MES, control-system, historian, or other connections without assuming every project uses the same architecture.

Test expected peak activity and agreed response times in a representative environment. Include external-system failures so the review covers more than uninterrupted operation.

Where applicable, verify retry behavior, duplicate detection, delayed messages, and recovery after interruption. Confirm that error messages reach someone responsible for acting on them.

Reconcile business results as well as message counts. Successful delivery does not establish that an order status, quantity, or material association is correct.

Define the authoritative comparison source for each reconciliation. Document any permitted tolerance and its justification. Investigate unexplained differences, and obtain approval from the relevant operational or quality owner before declaring the workflow ready.

Rehearse Cutover and Recovery as Operating Procedures

Cutover is the controlled transition into live operation. Its runbook should specify the sequence, dependencies, responsible personnel, verification steps, and decision checkpoints.

Include final data preparation, access checks, interface activation, and confirmation of the operating state. Rehearse the activities that can reasonably be tested outside production and confirm that they fit the available window.

Review cutover scripts and procedures with the people who will execute them. Each person should understand the instructions, their responsibilities, and the conditions that require escalation.

Recovery planning needs equal specificity. Rollback, restoring the prior technical state, is not always the same as operational fallback, using an approved alternative way of working.

Once live production transactions exist, restoring an earlier backup alone does not explain how subsequent activity will be preserved and reconciled. The plan must address those records and the state of connected systems.

Define recovery triggers, decision authority, transaction boundaries, and restart verification. If safe recovery or fallback cannot be demonstrated for the intended launch scope, reduce the scope or defer approval.

Establish Hypercare and Production Ownership

Hypercare is the period of elevated support immediately after launch. It should have defined coverage, escalation, monitoring, and exit criteria rather than an assumed end date.

Confirm that support personnel are trained, have the appropriate access, and understand ticket handling and escalation. Plan the handover from implementation to ongoing support before launch.

For MES, agree who watches interface failures, unprocessed transactions, application availability, and reconciliation exceptions. Establish how those technical signals reach production leadership when work is affected.

Rain Engineering’s Proficy Plant Applications services describe implementation, role-based training, and ongoing support. Those services belong in the readiness conversation before launch, when responsibilities and expectations can still be agreed.

Production ownership should remain with named business roles. The integrator and IT teams support the operation; they should not become the default authority for every production or quality decision.

Make the Approval Traceable

The final review should produce a recorded decision with approved scope, supporting evidence, accepted exceptions, and accountable owners.

A conditional approval needs explicit boundaries. Identify which conditions must be closed before activation and which accepted issues can remain afterward. Do not use “conditional go” to disguise an unresolved launch blocker.

A completed checklist is valuable, but the decision rests on what its answers demonstrate.

The plant is ready when required work can be performed, records can be trusted, support is available, and recovery responsibilities are understood.

After all, go-live is not simply the end of configuration… It is the point at which the business accepts responsibility for operating with MES.


FAQ

Q: What Should I Check Before Starting an MES Project?
A:
Establish objectives, current-state processes, team responsibilities, integration requirements, training needs, and success measures. Rain’s checklist organizes these considerations across the implementation lifecycle.

Q: How Do You Know an MES Is Ready for Go-Live?
A:
Use agreed acceptance criteria supported by completed testing, verified information, prepared users, support coverage, and business sign-off, rather than configuration completion alone.

Q: Must Every Defect Be Closed Before Launch?
A:
Not necessarily. Assess remaining issues against agreed blocking criteria and document any accepted risk, mitigation, owner, and resolution plan. An unresolved launch blocker should prevent approval.

Q: What Should Happen Immediately After Go-Live?
A:
Provide elevated support, monitor operation and adoption, resolve exceptions, and manage the transition to ongoing support against defined criteria.

P.S. The best time to define a successful go-live is before the launch meeting.

Rain Engineering’s MES Implementation Checklist helps teams review planning, deployment, training, and ongoing improvement together.

Use it to identify gaps early, then contact Rain Engineering to discuss the evidence, ownership, and support your team needs before saying yes to MES go-live.


Don Rahrig Avatar


More about this author   LinkedIn

Subscribe to Smart Factory Insights

Subscribe to Smart Factory Insights for topical blog posts,
timely industry news, and MES best practices –
keeping you in the conversation so you can do better.

* indicates required

<< Back to Blog Home